Schedule

Anticipated Progress

As the project attains confirmation of approval through the NEPA reevaluation process during the summer of 2026, final design will be completed for Phase 1 and construction is anticipated to begin during the first quarter of 2027.

A Gantt chart style project schedule, showing design work in 2026 and 2027, start of construction in early 2027, and completion of phase 1 in early 2031. Phase 2 will follow as funding allows.

Completed Tasks

2006

Environmental Assessment process completed and document submitted.

2007

Finding of No Significant Impact (FONSI) letter issued by FHWA, allowing project to proceed.

2022/23

Initial NEPA Reevaluation completed and approved to address early design changes.

2023

Commitment of TIFIA loan funds from US Dept. of Transportation and HB-ACT 443 to partially fund the project.

2023

Notice of Intent released by DOTD requesting Letters of Interest for the CMAR Contractor to deliver the project. Engineering design begins.

2026

Design refinements continue, addressing physical and financial constraints. Reevaluation #2 documentation preparation and submission to FHWA.

2027

Anticipated start of construction

2031

Anticipated completion of Phase 1